How To Install Liquid Cooling Ball Valve Better?
The installation steps of Ball Valve data center are as follows:
1. First, you need to remove the protective covers on both sides of the flange end, and then flush and clean the valve body of the cooling Ball Valve when it is fully opened.
2. Before installation, the whole machine should be tested according to the specified signal, and it can be installed online only after it is qualified.
3. When preparing for pipeline connection, you must first flush and clean the remaining impurities in the pipeline.
4. During installation, do not use the actuator part of the ball valve as a lifting point, otherwise it will damage the actuator and accessories.
5. This type of cooling water Ball Valve should be installed in the horizontal or vertical direction of the pipeline.
6. The pipeline near the installation point of the Ball Valve cooling must not be drooping or subjected to external forces. You can use pipe brackets or supports to offset the deviation of the pipeline.
7. After connecting to the pipeline, you can use the specified torque to cross-lock the flange and connect the bolts.